LOJ Turf Field

  • The LOJ turf field broke ground on May 21, 2018. The first phase is the creation of the water retention pond. This structure is going to be 90ft by 150ft by 6ft deep. It is mandated by the City of Lake Oswego. 
     
    The District estimates the field will be completed by late August. 
     
    Check back as we update the site with pictures of the project's progress.
Excavator and grader working on new turf field for Lake Oswego Junior High School

Grading for the field begins

Lake Oswego Junior High softball field being graded

As of May 30, installation of the water catchment system proceeds with 4' tubing and gravel