Palisades Renovations: August 2023

  • Project Status:

    Recently completed tasks include:
    - gym/physical education office: seismic upgrades, wall painting, clean-up, gym office carpet installed
    - classroom #31: carpet, paint, clean-up
    - hallway: seismic upgrades by gym wall, painting, clean-up
    - new transformer and switchgear
    - kitchen: new flooring, walk-in cooler & freezer, kitchen hood installed

    Current site activity includes:
    - mechanical equipment start-up
    - electrical: connections to new equipment and installation of new panels
    - installation of future chiller lines
    - kitchen equipment installation
    - re-roofing

    Phase 2 renovations scheduled for summer of 2024

Playground & Garden Updates: August 2023

  • Project Status:

    • Native garden at Palisades Elementary
      - majority of work has been completed
      - planting is the only pending work and is dependent
        on cooler weather
      - estimated completion date is October 20, 2023
    • Garden beds at Palisades Elementary
      - gravel pad and bed installation has been completed
      - irrigation connection is pending
      - end of August 2023 completion
    • Playground equipment at Palisades Elementary
      - playground installation has been completed

     

June 30, 2023

  • Project Status

    • Contractor fully mobilized to the school as of June 14
    • Abatement work in roof, boiler room, and kitchen has been
      completed
    • Saw cutting and removal of slab for underground
      connections in kitchen area has been completed
    • Seismic upgrades of gym in progress
    • Reroof of gym and kitchen continues
    • Mechanical scope continues in boiler room and kitchen
    • Phase 2 renovations scheduled for summer of 2024
    • Native garden at Palisades Elementary
      - Grasstains, LLC began construction of the native garden on June 27
      - Estimated completion date is July 21, 2023
    • Garden beds at Palisades Elementary
      - district is gathering bids from contractors to complete the construction of the gravel pad required for the garden beds
      - garden beds will be ready to install by end of August 2023
    • Playground equipment at Palisades Elementary
      - playground equipment has been ordered - delivery estimated for July 12
      - installation of equipment scheduled for the end of July 2023

Native Garden Under Construction

  • Native Garden under construction

    Native Garden under construction