Project Status:
Recently completed tasks include:
- gym/physical education office: seismic upgrades, wall painting, clean-up, gym office carpet installed
- classroom #31: carpet, paint, clean-up
- hallway: seismic upgrades by gym wall, painting, clean-up
- new transformer and switchgear
- kitchen: new flooring, walk-in cooler & freezer, kitchen hood installed
Current site activity includes:
- mechanical equipment start-up
- electrical: connections to new equipment and installation of new panels
- installation of future chiller lines
- kitchen equipment installation
- re-roofing
Phase 2 renovations scheduled for summer of 2024