Uplands Elementary School Renovations – Project Update June 2019

  • Bond Team for this project includes:

    Tony Vandenberg, Executive Director of Project Management
    Paul Eskeldson, Senior Project Manager
    Jamie Harwood, Project Coordinator
    DOWA-IBI Group – Design Team
    Triplett Wellman Contractors

    • In the classroom/admin areas, the contractor has completed the seismic upgrades, framing, mechanical, and plumbing rough-in and the roofing moisture barrier. Gypsum board is being installed along with plumbing fixtures
    • Work in the gym started after students were released for summer break
    • Installation of the 4-classroom modular building is underway and expected to be complete by the end of June
    • The classroom technology data cabling is underway
    • Oak Creek furniture and equipment will be moved into Uplands in phases as wings of the building are completed. The administrative office will move first in early July