Lake Oswego Junior High Renovations Project Update – December 2019

  • Bond Team for this project includes:
    Tony Vandenberg, Executive Director of Project Management
    David Kruger, Senior Project Manager
    Jamie Harwood, Project Coordinator
    OH Planning + Design: Design Team
    INLINE Construction – Construction Managers/General Contractor 

    Renovations include:

    • A modular building was added to the north side of campus this summer which includes five classrooms. This project is completed and received Final Certificate of Occupancy on August 21
    • The renovation project at Lake Oswego Junior High has been extended to incorporate a single occupant, accessible restroom. The restroom is completed and the project has received final inspections
    • The Innovation Lab has been completed and is fully operational
    • Secure vestibule doors and hardware are operational and the Raptor Visitor Management System is functional for visitors
    • The new gymnasium received a permit on October 3 and excavation started immediately
    • Excavation uncovered some underground structures that had to be decommissioned which set the schedule back 2-3 weeks. The decommissioning of the three dry wells has been completed
    • Building footings and slab have been poured and site work is continuing
    • Pre-engineered building is on site and construction started the week of December 16. Estimated completion date has been readjusted to the end of February 2020

New gym in progress

New gym at Lake Oswego Junior High School in progress